Cost Per Square Foot
Cost Per Square Foot
wdt_ID | Bid date | Building (Construction, without site development) | Construction (Construction, with site development) |
---|---|---|---|
1 | July 2003 | $138.75 | $155.40 |
9 | July 2004 | $140.00 | $156.80 |
10 | July 2005 | $157.00 | $175.84 |
11 | July 2006 | $190.00 | $212.80 |
12 | July 2007 | $215.00 | $240.80 |
13 | July 2008 | $215.00 | $240.80 |
14 | July 2009 | $224.00 | $250.88 |
15 | July 2010 | $200.00 | $224.00 |
16 | July 2011 | $200.00 | $224.00 |
17 | July 2012 | $207.00 | $231.84 |
18 | July 2013 | $215.00 | $240.80 |
19 | July 2014 | $224.00 | $250.88 |
20 | July 2015 | $233.00 | $260.96 |
21 | July 2016 | $282.00 | $335.58 |
22 | July 2017 | $293.00* | $348.67 |
23 | July 2018 | $302.00 | $360.00 |
24 | July 2019 | $318.00** | $378.00 |
25 | July 2020 | $329.00 | $391.51 |
26 | July 2021 | $341.00 | $405.00 |
105 | July 2022 | $358.00 | $426.00 |
106 | July 2023 | $385.00 | $458.00 |
107 | July 2024 | $404.00 | $481.00 |
Bid date | Building (Construction, without site development) | Construction (Construction, with site development) |
*The Interagency Commission on School Construction reexamined and revised the July 2017 cost per square foot for school construction on March 29, 2017.
**The IAC revised the July 2019 cost per square foot for school construction on August 30, 2018.